TRUPACT-II & HalfPACT TYPE B PACKAGES
|
TRUPACT-II, NRC Docket 71-9218 Rev 25 - Implemented on November 30th, 2020 |
TRUPACT-II, NRC Docket 71-9218 Rev 26 - Implemented on June 7th, 2022 |
TRUPACT-II, NRC Docket 71-9218 Rev 27 - Implemented on November 22nd, 2022 |
TRUPACT-II, NRC Docket 71-9218 Rev 28 - Implemented on October 22nd, 2024 |
Title |
Document No. |
Rev. |
Date |
TRUPACT-II NRC Certificate of Compliance |
- |
25 |
November 2020 |
TRUPACT-II NRC Certificate of Compliance |
- |
26 |
June 2022 |
TRUPACT-II NRC Certificate of Compliance |
- |
27 |
November 2022 |
TRUPACT-II NRC Certificate of Compliance |
- |
28 |
October 2024 |
TRUPACT-II Safety Analysis Report |
- |
24 |
August 2020 |
TRUPACT-II Safety Analysis Report |
- |
25 |
February 2022 |
TRUPACT-II Safety Analysis Report |
- |
26 |
November 2022 |
CH-TRAMPAC |
- |
5 |
August 2020 |
CH-TRAMPAC |
- |
6 |
February 2022 |
CH-TRU Payload Appendices |
- |
4 |
August 2020 |
CH-TRU Payload Appendices |
- |
5 |
February 2022 |
HalfPACT, NRC Docket 71-9279 Rev 9 - Implemented on November 30th, 2020
|
HalfPACT, NRC Docket 71-9279 Rev 10 - Implemented on June 7th, 2022 |
HalfPACT, NRC Docket 71-9279 Rev 11 - Implemented on November 22nd, 2022 |
Title |
Document No. |
Rev. |
Date |
HalfPACT NRC Certificate of Compliance |
- |
9 |
November 2020 |
HalfPACT NRC Certificate of Compliance |
- |
10 |
June 2022 |
HalfPACT NRC Certificate of Compliance |
- |
11 |
November 2022 |
HalfPACT Safety Analysis Report |
- |
7 |
August 2020 |
HalfPACT Safety Analysis Report |
- |
8 |
February 2022 |
HalfPACT Safety Analysis Report |
- |
9 |
November 2022 |
CH-TRAMPAC |
- |
5 |
August 2020 |
CH-TRAMPAC |
- |
6 |
February 2022 |
CH-TRU Payload Appendices |
- |
4 |
August 2020 |
CH-TRU Payload Appendices |
- |
5 |
February 2022 |
CH Payload
|
Title |
Document No. |
Rev. |
Date |
CH-TRUCON |
N/A |
N/A |
N/A |
CH Operations and Maintenance
|
Title |
Document No. |
Rev. |
Date |
CH Packaging Program Guidance |
DOE/WIPP-02-3183 |
12 |
May 2019 |
CH Packaging Operations Manual
| DOE/WIPP-02-3184 |
20 |
September 2024 |
CH Packaging Maintenance Manual |
DOE/WIPP-02-3185 |
4 |
November 2014 |
CH Packaging Operations for High Wattage Waste |
DOE/WIPP-02-3220 |
15 |
November 2014 |
Maintenance Record Form |
EA023183-1-0 |
0 |
January 2013 |
TRUPACT-II/HalfPACT Trailer Operation and Maintenance Manual |
WP 08-PT.04 |
10 |
February 2024 |
CH Quality Grading
|
Title |
Document No. |
Rev. |
Date |
Q-List and Quality Category Assessments for the TRUPACT-II Package |
TP2-QGR-0001 |
4 |
October 2018 |
Q-List and Quality Category Assessments for the HalfPACT Package |
HPT-QGR-0001 |
4 |
October 2018 |
CH Work Instructions
|
Title |
Document No. |
Rev. |
Date |
Replacement of ICV/OCV Small Plugs, O-Rings, and Gaskets |
CH.01 |
4 |
October 2013 |
Replacement of ICV/OCV Upper and Lower Main O-Rings, ICV Wiper O-Ring, OCA Fiber Gasket, and ICV Debris Shield |
CH.02 |
5 |
October 2013 |
Replacement of Miscellaneous Parts Not Requiring Detailed Instructions |
CH.03 |
3 |
October 2015 |
Chasing ICV/OCV Coupling, Fitting, and Insert Threads |
CH.04 |
1 |
April 2013 |
Replacement of Polyethylene Filter in ICV Lower Seal Flange |
CH.05 |
1 |
April 2013 |
Replacement of Threaded Inserts/Fasteners |
CH.06 |
2 |
February 2016 |
Replacement of Outer Confinement Vessel (OCV) Locking Z Flange |
CH.07 |
2 |
October 2013 |
Axial Play Measurement (OCV Lid to Body) (ICV Lid to Body) and Wear Pad Replacement |
CH.08 |
3 |
July 2019 |
ICV/OCV Lid & Body Seal Flange Tab Width Measurements |
CH.09 |
1 |
October 2013 |
ICV/OCV Lid & Body Seal Flange Groove Width Measurements |
CH.10 |
1 |
October 2013 |
ICV/OCV Upper Main O-Ring Seal Groove Depth Measurement and Surface Finish Inspection |
CH.11 |
1 |
October 2013 |
Minor Repair of ICV/OCV Seal Area Surface Finish and Vessel Wall |
CH.12 |
2 |
October 2013 |
Replacement, Inspection, or Measurement of Inner Containment Vessel (ICV) Honeycomb Spacers |
CH.13 |
3 |
October 2013 |
Minor Repair of ICV/OCV Locking Ring Surfaces (burrs, dings, and nicks) |
CH.14 |
1 |
October 2013 |
Annual and Five-Year Maintenance Inspections |
CH.15 |
1 |
October 2013 |
Repair of Inner Containment Vessel (ICV)/Outer Confinement Vessel (OCV) Locking Ring Stop Plate(s) |
CH.16 |
1 |
October 2013 |
Repair/Replacement of Inner Containment Vessel (ICV) Upper/Lower Spacer Bracket(s) |
CH.17 |
1 |
October 2013 |
Repair of ICV Upper/Lower Honeycomb Spacer |
CH.18 |
3 |
October 2013 |
Training Unit Fitness for Use Inspections |
CH.19 |
1 |
October 2013 |
Inner Containment Vessel (ICV) Replacement |
CH.20 |
1 |
October 2013 |
Inspection of Shielded Container Axial and Radial Dunnage, and Pallet Assemblies |
CH.22 |
1 |
July 2014 |
TRUPACT-III TYPE B PACKAGE
|
TRUPACT-III, NRC Docket 71-9305 - Implemented on October 24, 2013
|
Title |
Document No. |
Rev. |
Date |
TRUPACT-III NRC Certificate of Compliance |
- |
11 |
June 2020 |
TRUPACT-III Safety Analysis Report |
- |
15 |
July 2013 |
TRUPACT-III TRAMPAC |
- |
2 |
May 2010 |
TRUPACT-III Payload
|
Title |
Document No. |
Rev. |
Date |
TRUCON-III |
DOE/WIPP-11-3458 |
4 |
August 2019 |
TRUPACT-III Operations and Maintenance
|
Title |
Document No. |
Rev. |
Date |
TRUPACT-III Program Guidance |
DOE/WIPP-11-3456 |
6 |
July 2019 |
TRUPACT-III Operations Manual |
DOE/WIPP-11-3451 |
10 |
July 2019 |
Maintenance Record Form |
EA023183-1-0 |
0 |
January 2013 |
TRUPACT-III Trailer Operation and Maintenance Manual |
WP 08-PT.18 |
9 |
November 2023 |
TRUPACT-III Quality Grading
|
Title |
Document No. |
Rev. |
Date |
Quality List for the TRUPACT-III Package |
AREVA QL-027 |
11 |
March 2014 |
Q-List and Quality Category Assessments for the TRUPACT-III Packaging Miscellaneous Components |
TP3- QGR-0001 |
2 |
October 2014 |
TRUPACT-III Work Instructions
|
Title |
Document No. |
Rev. |
Date |
Replacement of Rings, Inserts, Plugs, and O-Ring Seals |
TP3.01 |
2 |
February 2012 |
Replacement of Closure Lid O-Rings and Debris Shield |
TP3.02 |
2 |
August 2012 |
Replacement of Miscellaneous Parts Not Requiring Detailed Instructions |
TP3.03 |
1 |
August 2012 |
Replacement of Overpack Cover and Closure Lid Attachment Bolts |
TP3.04 |
2 |
February 2017 |
Repairing Internal Threaded Holes |
TP3.05 |
0 |
May 2011 |
Seal Surface Finish Inspection |
TP3.06 |
0 |
May 2011 |
Minor Repair of O-ring Sealing Surface |
TP3.07 |
0 |
May 2011 |
Annual and Five-Year Maintenance Inspections |
TP3.08 |
1 |
October 2014 |
Roller Floor Inspection and Component Replacement |
TP3.09 |
0 |
May 2012 |
Replacement of Threaded Inserts |
TP3.10 |
0 |
June 2014 |
RH-TRU 72-B TYPE B PACKAGE
|
RH-TRU 72-B, NRC Docket 71-9212 - Implemented on March 29, 2017
|
Title |
Document No. |
Rev. |
Date |
RH-TRU 72-B NRC Certificate of Compliance |
- |
11 |
December 2019 |
RH-TRU 72-B Safety Analysis Report |
- |
7 |
December 2015 |
RH-TRAMPAC |
- |
3 |
December 2015 |
RH-TRU Payload Appendices |
- |
3 |
December 2015 |
RH Payload
|
Title |
Document No. |
Rev. |
Date |
RH-TRUCON |
DOE/WIPP-90-045 |
27 |
July 2015 |
RH Operations and Maintenance
|
Title |
Document No. |
Rev. |
Date |
RH Packaging Program Guidance |
DOE/WIPP-02-3283 |
7 |
February 2017 |
RH Packaging Operations Manual |
DOE/WIPP-02-3284 |
11 |
March 2017 |
RH Packaging Maintenance Manual |
DOE/WIPP-02-3285 |
7 |
May 2017 |
Maintenance Record Form |
EA023183-1-0 |
0 |
January 2013 |
RH-TRU 72-B Cask Uprighting Trailer Operation and Maintenance Manual |
WP 08-PT.13 |
9 |
October 2018 |
RH Quality Grading
|
Title |
Document No. |
Rev. |
Date |
Q-List and Quality Category Assessments for the RH-TRU 72-B Package |
72B-QGR-0001 |
0 |
November 2011 |
RH Work Instructions
|
Title |
Document No. |
Rev. |
Date |
Replacement of IV/OC Port Closure Bolts and O-rings |
RH.01 |
3 |
December 2011 |
Replacement of IV/OC Main O-rings |
RH.02 |
3 |
December 2011 |
Replacement/Repair of Lid Closure and Impact Limiter Attachment Bolts |
RH.03 |
2 |
December 2011 |
Replacement of Miscellaneous Parts Not Requiring Detailed Instructions |
RH.04 |
1 |
December 2011 |
Cleaning Threads and Replacing Thread Inserts |
RH.05 |
3 |
July 2013 |
IV/OC Sealing Surface Finish Inspection |
RH.06 |
2 |
February 2015 |
Minor Repair of IV and OC Lid and Body Exposed Surfaces |
RH.07 |
3 |
December 2011 |
Annual and Five-Year Maintenance Inspections |
RH.08 |
4 |
March 2012 |
Training Unit Fitness for Use Inspections |
RH.09 |
2 |
September 2016 |
Painting Markings on RH-TRU 72-B |
RH.10 |
1 |
November 2012 |
Replacement of Screws, Bolts and Washers on RH-72B Cask Uprighting
Trailers |
RH.12 |
2 |
December 2013 |
Repair of Hydraulic Couplers and Fluid Leaks on RH 72-B Trailers |
RH.14 |
1 |
September 2012 |
TYPE A PAYLOAD CONTAINERS
|
Criticality Control Overpack - For use in TRUPACT-II & HalfPACT
|
Title |
Document No. |
Rev. |
Date |
Criticality Control Overpack |
CCO-DWG-0001 |
6 |
February 2024 |
Specification for Fabrication of the Criticality Control Overpack |
CCO-SPC-0001 |
3 |
May 2018 |
Criticality Control Overpack Handling and Operation Manual |
CCO-MAN-0001 |
7 |
September 2024 |
Criticality Control Overpack Type A Evaluation Report |
CCO-REP-0001 |
3 |
December 2024 |
Q-list and Quality Category Assessments for the Criticality Control Overpack |
CCO-QGR-0001 |
2 |
February 2024 |
Drum Spacer - For use in TRUPACT-II & HalfPACT
|
Title |
Document No. |
Rev. |
Date |
Grout Spacer, 55-gal Drum |
DRSP-DWG-0001 |
0 |
September 2012 |
Grout Spacer, 100-gal Drum |
DRSP-DWG-0002 |
0 |
September 2012 |
Grate Spacer, 55-gal Drum |
DRSP-DWG-0003 |
0 |
September 2012 |
Grate Spacer, 100-gal Drum |
DRSP-DWG-0004 |
0 |
September 2012 |
Q-list and Quality Category Assessments for the Compacted Puck Drum Spacers |
DRSP-QGR-0001 |
0 |
July 2012 |
Pipe Overpack - For use in TRUPACT-II & HalfPACT
|
Title |
Document No. |
Rev. |
Date |
6-in. Standard Pipe Overpack |
POC-DWG-0001 |
3 |
June 2022 |
6-in. Pipe Component |
POC-DWG-0002 |
3 |
June 2022 |
6-in. Pipe Component Dunnage |
POC-DWG-0003 |
3 |
June 2022 |
S100 Pipe Overpack |
POC-DWG-0004 |
3 |
June 2022 |
12-in. Standard Pipe Overpack |
POC-DWG-0005 |
3 |
June 2022 |
12-in. Pipe Component |
POC-DWG-0006 |
3 |
June 2022 |
12-in. Pipe Component Dunnage |
POC-DWG-0007 |
3 |
June 2022 |
S200-A Pipe Overpack |
POC-DWG-0008 |
1 |
August 2013 |
S200-B Pipe Overpack |
POC-DWG-0009 |
1 |
August 2013 |
S300 Pipe Overpack |
POC-DWG-0010 |
2 |
May 2018 |
POC Rigid Drum Liner |
POC-DWG-0011 |
1 |
August 2013 |
Specification for Fabrication of the Pipe Overpack (Standard, S100, S200 and S300) |
POC-SPC-0001 |
3 |
June 2022 |
Pipe Overpack Handling and Operation Manual |
POC-MAN-0001 |
5 |
March 2024 |
Pipe Overpack Type A Evaluation Report |
POC-REP-0001 |
1 |
September 2013 |
Q-list and Quality Category Assessments for the Standard Pipe Overpacks |
POC-QGR-0001 |
4 |
June 2022 |
Q-list and Quality Category Assessments for the S100 Pipe Overpack |
POC-QGR-0002 |
3 |
June 2022 |
Q-list and Quality Category Assessments for the S200 Pipe Overpacks |
POC-QGR-0003 |
3 |
June 2022 |
Q-list and Quality Category Assessments for the S300 Pipe Overpack |
POC-QGR-0004 |
3 |
June 2022 |
Shielded Container Assembly - For use in HalfPACT
|
Title |
Document No. |
Rev. |
Date |
Shielded Container Assembly |
SCA-DWG-0001 |
2 |
January 2021 |
SC-30G2 Shielded Container Assembly |
SCA-DWG-0007 |
1 |
February 2021 |
SC-30G3 Shielded Container Assembly |
SCA-DWG-0011 |
1 |
February 2021 |
SC-55G1 Shielded Container Assembly |
SCA-DWG-0013 |
1 |
February 2021 |
SC-55G2 Shielded Container Assembly |
SCA-DWG-0016 |
1 |
February 2021 |
Specification for Fabrication of the Shielded Container Assembly |
SCA-SPC-0001 |
3 |
June 2022 |
Shielded Container Assembly Handling and Operation Manual |
SCA-MAN-0001 |
3 |
November 2024 |
SC-30G1 Shielded Container Type A Evaluation Report |
SCA-REP-0001 |
2 |
February 2024 |
SC-30G2 Shielded Container Type A Evaluation Report |
SCA-REP-0002 |
0 |
February 2024 |
SC-30G3 Shielded Container Type A Evaluation Report |
SCA-REP-0003 |
0 |
February 2024 |
SC-55G1 Shielded Container Type A Evaluation Report |
SCA-REP-0004 |
0 |
February 2024 |
SC-55G2 Shielded Container Type A Evaluation Report |
SCA-REP-0005 |
0 |
February 2024 |
Q-list and Quality Category Assessments for the Shielded Container Assembly |
SCA-QGR-0001 |
1 |
September 2023 |
Q-list and Quality Category Assessments for the SC-30G2 Shielded Container Assembly |
SCA-QGR-0002 |
1 |
April 2021 |
Q-list and Quality Category Assessments for the SC-30G3 Shielded Container Assembly |
SCA-QGR-0003 |
2 |
April 2021 |
Q-list and Quality Category Assessments for the SC-55G1 Shielded Container Assembly |
SCA-QGR-0004 |
2 |
April 2021 |
Q-list and Quality Category Assessments for the SC-55G2 Shielded Container Assembly |
SCA-QGR-0005 |
1 |
April 2021 |
Standard Waste Box - For use in TRUPACT-II & HalfPACT
|
Title |
Document No. |
Rev. |
Date |
Standard Waste Box Assembly |
SWB-DWG-0001 |
0 |
April 2024 |
Specification for Fabrication of the Standard Waste Box |
E-I-343 |
14 |
June 2020 |
Standard Waste Box Handling and Operation Manual |
WP 08-PT.01 |
11 |
May 2022 |
Standard Waste Box Type A Evaluation Report |
SWB-REP-0001 |
1 |
January 2015 |
Ten Drum Overpack - For use in TRUPACT-II
|
Title |
Document No. |
Rev. |
Date |
TRUPACT-II Ten Drum Overpack Assembly |
TDOP-DWG-0001 |
0 |
April 2024 |
Specification for Fabrication of the Ten Drum Overpack |
E-I-430 |
11 |
June 2020 |
Ten Drum Overpack Handling and Operation Manual |
WP 08-PT.02 |
11 |
June 2020 |
Ten Drum Overpack Type A Evaluation Report |
TDOP-REP-0001 |
2 |
January 2015 |
Standard Large Box 2 - For use in TRUPACT-III
|
Title |
Document No. |
Rev. |
Date |
Standard Large Box 2 Assembly (SLB2) Top Loading |
SLB2-DWG-0001 |
0 |
April 2024 |
Standard Large Box 2 Assembly (SLB2) Bottom Loading |
SLB2-DWG-0002 |
0 |
April 2024 |
Specification for Fabrication of the Standard Large Box 2 |
E-I-463 |
9 |
June 2020 |
TRUPACT-III Standard Large Box 2 Handling and Operation Manual |
WP 08-PT.05 |
7 |
June 2020 |
Standard Large Box 2 Type A Evaluation Report |
SLB2-REP-0001 |
0 |
January 2015 |
Removable Lid Canister - For use in RH-TRU 72-B
|
Title |
Document No. |
Rev. |
Date |
Removable Lid Canister |
RLC-DWG-0001 |
2 |
July 2015 |
Sealed Spring Plunger |
RLC-DWG-0002 |
2 |
July 2015 |
Specification for Fabrication of the Removable Lid Canister |
RLC-SPC-0001 |
2 |
August 2013 |
Removable Lid Canister Handling and Operation Manual |
RLC-MAN-0001 |
1 |
August 2013 |
Removable Lid Canister Type A Evaluation Report |
RLC-REP-0001 |
3 |
June 2016 |
Q-list and Quality Category Assessments for the RH Removable Lid Waste Canister |
RLC-QGR-0001 |
2 |
December 2012 |
Q-list and Quality Category Assessments for the Removable Lid Canister Miscellaneous Components |
RLC-QGR-0002 |
1 |
December 2012 |
Neutron Shielded Canister - For use in RH-TRU 72-B
|
Title |
Document No. |
Rev. |
Date |
NS15 Neutron Shielded Canister |
NSC-DWG-0001 |
3 |
September 2015 |
NS30 Neutron Shielded Canister |
NSC-DWG-0002 |
3 |
September 2015 |
Neutron Shielded Canister Handling and Operation Manual |
NSC-MAN-0001 |
2 |
June 2016 |
Neutron Shielded Canister Type A Evaluation Report |
NSC-REP-0001 |
2 |
June 2016 |
Q-list and Quality Category Assessments for the RH Neutron Shielded Waste Canister |
NSC-QGR-0001 |
1 |
December 2012 |
GENERAL
|
Guides
|
Title |
Document No. |
Rev. |
Date |
Recovery Guide for TRU Waste Packages |
DOE/CBFO-94-1007 |
9 |
January 2025 |
Procedures/Specifications
|
Title |
Document No. |
Rev. |
Date |
General Fabrication Specification for Packaging Related Parts/Tools |
GEN-SPC-0001 |
1 |
August 2013 |
CBFO Approved Filter Vents |
DOE/WIPP-11-3384 |
20 |
January 2024 |
Waste Isolation Pilot Plant Flammable Gas Analysis |
DOE/WIPP-06-3345 |
13 |
August 2023 |
Plans
|
Title |
Document No. |
Rev. |
Date |
Quality Assurance Program Plan for TRUPACT-II Gas Generation Test Program |
DOE/WIPP-01-3187 |
6 |
February 2020 |